Tomorrow
Mainframe system time begins at 2:00AM Monday mornings. The system is shutdown to a minimal state to allow for a pristine snapshot of all DASD volumes. Maintenance and upgrades are typically scheduled during this time as well. An IPL is performed before production services are made available by 6:00AM.
Wednesday, October 4th
Northwest Regional Data Center (NWRDC) would like to inform you upcoming BaaS maintenanceService(s): Atlanta Backup and Recovery ServicesMaintenance Start Time: Wednesday, October 4, 2023 0900 (ET)Maintenance End Time: Wednesday, October 4, 2023 2000 (ET)Service Availability: Atlanta BaaS Service InterruptionDetails: We will be performing a hardware upgrade to the Data Domain in Atlanta. During the maintenance, this Atlanta Data Domain and Atlanta Backup and Recovery Services will be offline, and there will be no backup or recovery activities possible for the Atlanta Avamar or Atlanta Networker during the upgrade. We will make our best effort to keep the outage as short as possible. We thank you for your patience as we work to improve Backup and Recovery services at the data center. Questions?We are here to help. If you experience issues after the maintenance has concluded or have any questions, please contact the NWRDC Operations Team at (850) 645-3500, it_support@nwrdc.fsu.edu.
Friday, October 6th
Meeting of the NWRDC Policy Board. If you are interested in attending this meeting, please contact kate_wasson@nwrdc.fsu.edu.
Monday, October 9th
Mainframe system time begins at 2:00AM Monday mornings. The system is shutdown to a minimal state to allow for a pristine snapshot of all DASD volumes. Maintenance and upgrades are typically scheduled during this time as well. An IPL is performed before production services are made available by 6:00AM.
Monday, October 16th
Mainframe system time begins at 2:00AM Monday mornings. The system is shutdown to a minimal state to allow for a pristine snapshot of all DASD volumes. Maintenance and upgrades are typically scheduled during this time as well. An IPL is performed before production services are made available by 6:00AM.
Monday, October 23rd
Mainframe system time begins at 2:00AM Monday mornings. The system is shutdown to a minimal state to allow for a pristine snapshot of all DASD volumes. Maintenance and upgrades are typically scheduled during this time as well. An IPL is performed before production services are made available by 6:00AM.
Monday, October 30th
Mainframe system time begins at 2:00AM Monday mornings. The system is shutdown to a minimal state to allow for a pristine snapshot of all DASD volumes. Maintenance and upgrades are typically scheduled during this time as well. An IPL is performed before production services are made available by 6:00AM.
Monday, November 6th
Mainframe system time begins at 2:00AM Monday mornings. The system is shutdown to a minimal state to allow for a pristine snapshot of all DASD volumes. Maintenance and upgrades are typically scheduled during this time as well. An IPL is performed before production services are made available by 6:00AM.